πŸ—οΈWEEK-END UPDATE: HRGS🌊

If you're looking at HRGS from Manhattan, you'll have a better view soon! The team is shifting the cofferdam east toward the shore. Deep Soil Mixing also continues inside the cofferdam. We've now mixed more than 428 soilcrete columns.

01.08.2025 18:45 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Building something as complex as the Hudson Tunnel Project takes top engineering talent. We are thrilled to welcome Jim Starace to the GDC team as Chief of Program Delivery! Read our press release announcing the news here: www.gatewayprogram.org/wp-content/u...

28.07.2025 18:37 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

🚧WEEK-END UPDATE: Manhattan Tunnel ProjectπŸ™οΈ

The MTP team has completed test pit excavations at Block 675 and Hudson River Park. Next step: starting construction of the slurry walls for the 12th Avenue Shaft.

25.07.2025 15:17 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image Post image Post image

With two projects more than 50% complete, key pieces of the new tunnel are starting to take shape! Click the link to see the latest pictures showing our progress on both sides of the Hudson River – and in it! www.gatewayprogram.org/photo-galler...

24.07.2025 17:24 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0

The Gateway Development Commission will hold an in-person public Board Meeting on Monday, July 28, 2025, at 11:00 am.

Registration and public comment information can be found here: www.gatewayprogram.org/board-meetin...

21.07.2025 13:41 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸš‚WEEK-END UPDATE: Palisades Tunnel Project🚧
You’ve got to go up to go down at the Palisades Tunnel Project site. The team built a massive ramp to install secant piles that will stabilize the sides of the launch point for the boring machines that will dig this section of tunnel.

18.07.2025 15:30 β€” πŸ‘ 2    πŸ” 1    πŸ’¬ 0    πŸ“Œ 0
Preview
The 2025 Trailblazers in Transportation Local leaders keeping New York on the move.

We're proud to see our CEO, Tom Prendergast, on City & State's Trailblazers in Transportation list. The Hudson Tunnel Project will transform travel into, out of, and through New York, setting the stage for the city and the region to thrive. www.cityandstateny.com/power-lists/...

14.07.2025 18:56 β€” πŸ‘ 1    πŸ” 1    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸš‰WEEK-END UPDATE: Tonnelle AvenueπŸš‚

This week, the Tonnelle Ave team implemented the final traffic switch, moving traffic into the newly-built middle section of the bridge. This marks the beginning of the final phase of work on this project!

11.07.2025 15:05 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Preview
Five Gateway Tunnel construction sites work toward 2035 completion There are 10 construction sites total.

Thousands of workers are hard at work building the Hudson Tunnel Project on both sides of the Hudson River, and in it. @samanthaliebman.bsky.social gives you an inside look at the work in progress for @spectrumnewsny1.bsky.social. ny1.com/nyc/all-boro...

10.07.2025 13:26 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0

One year since GDC secured full funding for the HTP and five of our construction packages are underway, on schedule and on budget. @gregmocker.bsky.social’s latest for PIX11 News shows the progress our crews are making on the ground, and under it, at all five sites. pix11.com/news/see-cre...

09.07.2025 16:43 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

One year ago today, we signed the Full Funding Grant Agreement for the Hudson Tunnel Project. Today we have five projects under construction supporting 20,000+ jobs. We’ve got a long way to go, but we’re off to a strong start!

08.07.2025 12:48 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸ”¨WEEK-END UPDATE: HYCC-3 πŸš‚
Excavation continues at the HYCC-3 construction site in Manhattan. The trench that will hold the tunnel box is now 60 feet deep, at the deepest point. The teams have removed more than 50,000 tons of soil and 1.7 million gallons of water.

03.07.2025 12:36 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Preview
Spotlight On: Balpreet Grewal-Virk, New Jersey Commissioner & Co-Chair, Gateway Development Commission - Capital Analytics Associates Gateway's Hudson Tunnel Project reshapes U.S. infrastructure, creating jobs and boosting rail capacity.

GDC’s NJ Co-Chair, Balpreet Grewal-Virk, was featured in caa's Spotlight On: series talking about the Hudson Tunnel Project.

Read the full interview here: capitalanalyticsassociates.com/spotlight-on...

02.07.2025 14:24 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Tom Wright and Carlo Scissura are right: New York doesn't work without reliable train service. Their great op-ed in @crainsnewyork.bsky.social highlights why we must keep the Hudson Tunnel Project on track.

Read the op-ed here: www.crainsnewyork.com/op-ed/keep-g...

01.07.2025 22:39 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Cofferdams date back to the Roman Empire, but are still used for construction today. We’re using one in the Hudson River to enable work stabilizing a section of the riverbed for tunnel boring.

Read our new blog post to learn more: mailchi.mp/gatewayprogr...

01.07.2025 15:06 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0

We are pleased to welcome Victor Herlinsky, Jr. to the GDC Board of Commissioners. Read statements from our CEO and Commission Co-Chairs here: www.gatewayprogram.org/wp-content/u...

30.06.2025 16:22 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Now that summer is here, we're preparing for in-water work on the Hudson River Ground Stabilization project to resume, shifting the temporary cofferdam in the Hudson River east toward Manhattan. Work to stabilize the riverbed for tunnel boring will continue inside the cofferdam.

27.06.2025 16:04 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Thousands of men and women work on building the Hudson Tunnel Project every day. For many, this is more than a job. It’s an opportunity to build a legacy.

Watch our new video to hear what the Hudson Tunnel Project means to the people building it: www.youtube.com/watch?v=YDTE...

25.06.2025 16:17 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

🚧WEEK-END UPDATE: Manhattan Tunnel ProjectπŸ™οΈ

Construction of the Manhattan Tunnel Project kicked off with the demolition of existing structures on the construction site. This is an important first step to make space for the work involved with building this section of the tunnel.

20.06.2025 13:45 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Today we launched The GDC Gazette, a quarterly newsletter with the latest info about what’s happening on the Hudson Tunnel Project.

From construction updates to fun facts about the tunnel, this newsletter has it all!

Read the first edition here: mailchi.mp/gatewayprogr...

18.06.2025 15:44 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Construction of NY and NJ Highline Tunnel hits halfway mark
YouTube video by PIX11 News Construction of NY and NJ Highline Tunnel hits halfway mark

Much of tunnel work is hidden – but not HYCC-3. We just crossed the halfway point on this project, and anyone can see our progress from the High Line.

PIX 11 takes you inside the project, with an up-close look at construction and interviews with workers.

www.youtube.com/watch?v=2f7N...

13.06.2025 16:26 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸš‚WEEK-END UPDATE: Palisades Tunnel Project🚧

The Hudson County Shaft is starting to take shape! This shaft will be used to switch the tunnel boring machines that dig through the Palisades with machines that are optimized for digging through the soft silt under the Hudson River.

13.06.2025 14:03 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸš‰WEEK-END UPDATE: TONNELLE AVEπŸ›€οΈ

The gateway to Gateway is coming together! Stage 2 of the Tonnelle Ave. Project is nearly complete. Soon traffic will shift to the middle section of the bridge, setting the team up to finish the final portion of this project.

06.06.2025 14:26 β€” πŸ‘ 0    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Video thumbnail

Construction of the Hudson Tunnel Project is supporting thousands of jobs and billions in economic activity. We talked with workers building the new tunnel about what the project means to them, their families, and their communities. Watch the full video at www.gatewayprogram.org/video-galler...

03.06.2025 13:48 β€” πŸ‘ 10    πŸ” 3    πŸ’¬ 0    πŸ“Œ 2
Post image

πŸš‰ WEEK-END UPDATE: Manhattan Tunnel ProjectπŸ™οΈ
Work has started on the MTP! Investigatory geotechnical boring is in progress to understand the exact makeup of the fill that the team will tunnel through and identify obstructions that will need to be removed or navigated around.

30.05.2025 16:45 β€” πŸ‘ 2    πŸ” 1    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸ—οΈWEEK-END UPDATE: HRGS🌊

We’re making steady progress on the Hudson River Ground Stabilization Project! The team removed obstructions in the current work area and is now mixing concrete into the soil in columns and wedges. So far, 250 columns and 6 wedges are installed.

23.05.2025 15:38 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Video thumbnail

We are are thrilled to announce that the HYCC-3 Project has reached the halfway point on schedule! This project is building the last section of the rail right-of-way beneath Hudson Yards that will connect the new tunnel to NY Penn Station. Learn more at www.gatewayprogram.org/wp-content/u...

20.05.2025 15:00 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

πŸš‚ WEEK-END UPDATE: Palisades Tunnel ProjectπŸš§β€―

Work to prepare the entry point for the TBMs continues! The team has finished soil sampling, site clearing, and geotechnical boring at the Tonnelle Ave. site.

16.05.2025 16:26 β€” πŸ‘ 2    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0
Post image

Today GDC hosted an industry networking event for subcontractors looking to meet with the proposers on two HTP construction contracts.

Small businesses can get the latest updates on HTP opportunities by registering in our vendor portal: www.gatewayprogram.org/vendor-porta...

13.05.2025 21:04 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0

The Gateway Development Commission will hold a public Board meeting on May 20, 2025, at 10:00 A.M. Registration and public comment information can be found here: www.gatewayprogram.org/board-meetin...

13.05.2025 13:43 β€” πŸ‘ 1    πŸ” 0    πŸ’¬ 0    πŸ“Œ 0