NNSA said it plans to implement new processes, including the use of templates and root cause guidance, to help project managers better meet reporting requirements. We recommend they complete the guidance and implement the process.
30.09.2025 16:27 โ ๐ 2 ๐ 1 ๐ฌ 0 ๐ 0
NNSA saw costs grow >25% on 7 out of 14 construction projects, but didnโt notify Congress about 5 of them for months, let alone within the 30 days required by law. Nor did NNSA assess the root causes of cost overruns for those 5 within 90 days or inform Congress, as required. #nukesky
30.09.2025 16:27 โ ๐ 0 ๐ 2 ๐ฌ 1 ๐ 0
NNSA spends a lot of money on nuclear weapons & infrastructure. NNSA has requirements (similar to those of the Nunn-McCurdy Act) to formally notify Congress about cost overruns and assess the reasons for the overruns, but it hasnโt consistently done so.
www.gao.gov/products/gao...
30.09.2025 16:26 โ ๐ 4 ๐ 5 ๐ฌ 1 ๐ 0
Los Alamos looks forward to additional park-and-ride shuttle routes to the lab. NNSA has some concerns about potential challenges with having sufficient federal staff to oversee the program and assess whether itโs providing the intended benefits.
30.09.2025 16:23 โ ๐ 0 ๐ 1 ๐ฌ 0 ๐ 0
Under a new authority in the FY25 NDAA, NNSA sites can reimburse some contractor commuting costs. This could improve safety and congestion. To date, Los Alamos is the only site to have made a proposal; they estimated it would cost $74 million to implement from FY25โ30.
30.09.2025 16:22 โ ๐ 1 ๐ 1 ๐ฌ 1 ๐ 0
Commuting can be a slog. One way NNSA can address recruitment & retention challenges at its labs is by making it easier to get to work, including by offering park-and-ride shuttles and public transit subsidies.
www.gao.gov/products/gao...
30.09.2025 16:22 โ ๐ 2 ๐ 1 ๐ฌ 2 ๐ 0
Until the UPF is ready, NNSA will have to keep using an 80-year old facility that could cost up to a half billion dollars to maintain in the meantime. We recommended that NNSA develop a comprehensive plan for this maintenance.
18.09.2025 17:04 โ ๐ 1 ๐ 1 ๐ฌ 0 ๐ 0
The UPF is also delayed. The agency is monitoring the project, but there are already doubts that the contractor will meet its project milestone for 2029. There are concerns about the ability to track project progress because of the way the contractor categorizes project tasks.
18.09.2025 17:04 โ ๐ 1 ๐ 1 ๐ฌ 1 ๐ 0
The estimated cost to complete the UPF has increased nearly $4 billion just since construction started in 2018. Poor management accounts for $770 million of that. NNSA has conducted reviews to get to the root of the cost increases and implemented 19 out of 20 corrective actions.
18.09.2025 17:03 โ ๐ 0 ๐ 1 ๐ฌ 1 ๐ 0
In 2004 NNSA began planning the Uranium Processing Facility to replace Manhattan Project-era facilities at Y-12 in TN. Fast forward 21 years: UPFโs est. cost is up to nearly $10 billion and itโll cost NNSA to keep using old facilities until UPF is complete.
www.gao.gov/products/gao...
18.09.2025 17:02 โ ๐ 1 ๐ 3 ๐ฌ 1 ๐ 0
We are starting work on just this issue! Want to get to the root causes.
10.09.2025 16:51 โ ๐ 1 ๐ 0 ๐ฌ 0 ๐ 0
This morning @nytimes reported on radiological risks in Ukraine. We have a recent report on the range of nuclear security and safety risks related to the war in Ukraine. www.gao.gov/products/gao...
10.09.2025 16:50 โ ๐ 1 ๐ 1 ๐ฌ 1 ๐ 0
As NNSAโs contractors underestimate the costs of the contracts across the enterprise, higher costs for small projects add up. We recommend NNSA ensure its contractors estimate costs more reliably to enable more realistic program planning & budgeting and better project management.
09.09.2025 18:58 โ ๐ 0 ๐ 0 ๐ฌ 0 ๐ 0
Over the next 2 decades, the United States plans to spend tens of billions of dollars to modernize its nuclear weapons stockpile. These expenditures will include hundreds of millions of dollars a year in fixed-price construction subcontracts.
09.09.2025 18:58 โ ๐ 0 ๐ 0 ๐ฌ 1 ๐ 0
You wouldnโt think the cost of a fixed-price construction contract could increaseโbut hundreds of NNSAโs run over, to the tune of $37.5 million just in FY23. NNSAโs construction budget is always tight so unexpected increases mean delays for other projects. www.gao.gov/products/gao... #nukesky
09.09.2025 18:57 โ ๐ 2 ๐ 3 ๐ฌ 2 ๐ 0
NNSAโs plans for upgrading one of the facilities are no longer current and the agency hasn't evaluated its progress on repairing any of the three. We recommend that NNSA develop performance measures to track and report on its progress, and document options for future upgrades.
05.09.2025 14:15 โ ๐ 4 ๐ 0 ๐ฌ 0 ๐ 0
In 2023 NNSA submitted to Congress a plan for repairing & upgrading these facilities. But the plan doesnโt give Congressโor other decision-makers, like NNSA managementโall the information they need to determine whether the fusion facilities can continue to perform as designed.
05.09.2025 14:15 โ ๐ 5 ๐ 1 ๐ฌ 1 ๐ 1
Fusion is essential for powering the USS Enterpriseโand, here on earth, for maintaining and modernizing the U.S. nuclear stockpile without explosive nuclear testing. NNSA operates 3 fusion facilities for these purposes.
www.gao.gov/products/gao... #nukesky
05.09.2025 14:14 โ ๐ 11 ๐ 3 ๐ฌ 4 ๐ 1
We pointed out some additional opportunitiesโfor example, DNFSB should revise its human capital plan to include more details on how the Board will achieve its goals, and by when. This will support performance by ensuring that staff responsibilities are well defined.
04.09.2025 15:49 โ ๐ 0 ๐ 0 ๐ฌ 0 ๐ 0
But! DNFSB is supposed to have 5 presidentially nominated & Senate-confirmed Board members. Filling seats has been challenging; as of August 2025, the Board had 2 seats filled, with 1 memberโs term expiring in Oct 2025. With 1 seated member, the Boardโs authority will be limited.
04.09.2025 15:47 โ ๐ 1 ๐ 1 ๐ฌ 1 ๐ 0
DNFSB has been busyโin addition to independently overseeing health & safety protections at U.S. defense nuclear facilities, it has been improving its management and planning based on recommendations from GAO and others.
04.09.2025 15:43 โ ๐ 0 ๐ 1 ๐ฌ 1 ๐ 0
Or if you preferโฆfission chipsโฆas your main meal, check out our weapons Quick Look. www.gao.gov/products/gao...
21.08.2025 13:48 โ ๐ 0 ๐ 0 ๐ฌ 0 ๐ 0
There is a list on our web site of the unclassified titles of sensitive and classified (restricted) reports that we issue. It is regularly updated.
21.08.2025 13:47 โ ๐ 1 ๐ 0 ๐ฌ 0 ๐ 0
I don't find classification to be an impediment to the work, but we aren't always able to issue our work publicly. Our preference is to issue our work publicly whenever possible, which sometimes means a public version in which we note the type of information that was removed for classification.
21.08.2025 13:46 โ ๐ 1 ๐ 0 ๐ฌ 2 ๐ 0
Cesium is so old school. There are much more cutting-edge ways to irradiate your shrimp. www.gao.gov/products/gao...
21.08.2025 13:42 โ ๐ 2 ๐ 1 ๐ฌ 0 ๐ 0
To address the cost estimate issue, we also recommend that the OIG develop life cycle cost estimates for conducting incurred cost audits. This would provide the OIG and decisionmakers a better understanding of cost-effective approaches and anticipated long-term costs.
24.07.2025 19:23 โ ๐ 1 ๐ 0 ๐ฌ 1 ๐ 0
In addition, while the OIGโs audit manual met standards regarding key issues like ethics, independence, and professional judgment, we found that it was missing certain procedures for fieldwork, reporting, and peer review standards. The OIG has since updated its manual.
24.07.2025 19:23 โ ๐ 0 ๐ 0 ๐ฌ 1 ๐ 0
The OIG based its estimate on limited data and opted for a โRough Order of Magnitudeโ estimate rather than a more thorough โLife Cycle Cost Estimate,โ which wouldโve been more suitable for supporting budgetary decisions, including determining the most cost-effective approaches.
24.07.2025 19:23 โ ๐ 1 ๐ 0 ๐ฌ 1 ๐ 0
Department of Energy: Inspector Generalโs Budget Estimates for Audits of Certain Contractorsโ Costs Need Improvement
The Department of Energyโs Office of Inspector General seeks to prevent fraud, waste, and abuse. In 2021 the OIG established a new division to audit...
#nukesky When DOEโs Office of the Inspector General set up a division for auditing DOEโs largest contractors in 2021, it estimated it would cost ~$19 million/year to operateโฆ but, as of 2025, the cost turns out to be more like $43.7 million.
24.07.2025 19:22 โ ๐ 1 ๐ 2 ๐ฌ 2 ๐ 0
Fully implementing our recommendations would provide NNSA and Congress with better cost information for budgetary decision-making on nuclear weapons and reduce duplicative data requests and reporting burdens for contractors.
23.07.2025 19:37 โ ๐ 1 ๐ 0 ๐ฌ 0 ๐ 0
Entrepreneur
Costplusdrugs.com
Director, Global Risk at Federation of American Scientists, former Sr. Dir NSC, Bulletin of Atomic Scientists (doomsday clock setter). Pope of Chili Town. No #manels, Yankees/Gunners.
Operations Director. Previously TIME, VICE News and the Village Voice. Posting about media, technology and the future of work. Learn more: https://tylerborchers.com
Deputy Managing Editor for Global Security at Politico
Big badda booms. Systems, process, and requirements.
Nuke nerd. Not my employer, likes/RTs โ endorsements
Military background, researcher, providing CBRN Risk assessment, observing Non-Proliferation efforts, CBRN OSINT.... โข๏ธโฃ๏ธโ ๏ธ๐ฝ
๐ด๓ ง๓ ข๓ ณ๓ ฃ๓ ด๓ ฟ๐ฌ๐งExecDir James Martin Center for Nonproliferation Studies DC @miis Past @DefenceHQ, @warstudies. Nonpro, emerging tech, China. Nuc engineer. Phd War Studies. http://nonproarchive.com
A nonprofit, nonpartisan global security organization focused on reducing nuclear, biological, and emerging tech threats imperiling humanity.
Nuclear weapons policy wonk. Opinions my own.
RTsโ endorsements. he/him/his
Director, Global Security Program @Union of Concerned Scientists. Working to reduce the risk of nuclear war, address the injustice and harm done by nuclear weapons, and move us closer to a world free from nuclear weapons. Oxford Comma enthusiast.
Political scientist at Brown, focusing on nuclear weapons, WMD, norms and institutions in security, human rights, ethics and laws of war.
Nuclear nerd and lover of baseball. Owner of the cutest dog in the world.
Fmr. FAS, CAP, CFR, Ph.D. Government, Georgetown.
Deterrence, nuclear strategy, progressive foreign policy.
Banners @UAHIRISE.
Nuke policy starter pack! https://go.bsky.app/8jiQV43
Nuclear weapons policy, history, culture, and other things to help you sleep. Comms Director and Sr Fellow, @councilonstrategicrisks.org. Teaching and such at Harvard Extension.
Stanton Senior Fellow, Carnegie Endowment for International Peace; Author of โTHE NEW NUCLEAR AGEโ (Polity) & โKIM JONG UN AND THE BOMBโ (Hurst/Oxford)
Subscribe to my newsletter (Nukesletter): https://panda.substack.com/
Senior Fellow, Carnegie Endowment. Defense analysis with a focus on the Russian and Ukrainian militaries.